What Goes Into the Cost of a Modular ADU in Montana
By Bill Chopp
The short answer: the cost of a modular ADU in Montana is the factory price of the unit plus everything it takes to get that unit onto your lot, set on a foundation and hooked up. The factory price is the number you see first, but on most projects the site side is a real share of the total, and it's the part that changes the most from one lot to the next. This post walks through everything that goes into it.
Here's how I'd break it down if you were sitting across the table from me.
Part 1: The factory price
Every price on our site, from small units like the Cabana 200 up to the Morada 800, is a factory starting price for the unit itself. Starting prices do not include site work, foundation, utilities, permits, transportation, or the crane set. Size, layout, and the finishes and options you pick during design all move the factory number too.
What you get for that number is the building: framed, wired, plumbed and finished in a factory, then shipped in modules. In Montana, factory-built buildings sold here have to carry a state insignia, and the plans and the factory's quality control are reviewed under the state's Factory-Built Buildings program at the Department of Labor & Industry. That's a big part of why the factory side of the budget is predictable: the design is fixed and reviewed before anything ships.
One more thing about how the money moves: payments for the home go directly to the manufacturer, our factory partner, not through us.
Part 2: Everything that happens on your lot
This is where budgets get surprised. On our guide page we list what a finished project includes beyond the home itself:
- Engineering and permits. Your local building department reviews the foundation and site plan and inspects the work done on site.
- Excavation and foundation. Crawl space, basement or slab. Soil, slope and frost depth drive this number more than square footage does.
- Transportation. Trucking the modules from the factory to your site. Distance and road access matter.
- Crane and set. The modules are lifted onto the foundation. A tight backyard, power lines, or a long reach over the main house can change the crane size and the cost.
- Utility connections. Water, sewer or septic, power, and sometimes gas, run from where they are now to where the ADU will sit. Trenching distance is a big variable.
- Septic and well, if needed. More on this below.
- Site and finish work. Steps, decks, grading, driveway or path, and the final details once the unit is set.
None of these are factory items, and none of them are done by us. We're a dealer: we help you pick the right unit, coordinate with the factory, and work alongside partner contractors who bid and build the site side. You contract and pay for that work directly.
The line items that swing the most
I can't give you an honest per-square-foot "all-in" number for Montana, because two lots on the same street can come out very differently. These are the items I'd look at first on any property.
Septic and well
If you're on city sewer and water, you're mostly paying for connections and any city fees. If you're rural, the ADU usually needs approval on the wastewater side before anything else moves.
In Montana, non-public septic systems need a local health permit, and new lots under 20 acres go through DEQ review (or a county that's contracted to do it) before a plat or certificate of survey is recorded, according to Montana DEQ's summary of septic permitting. Health departments size systems by bedroom count. For example, RiverStone Health in Yellowstone County asks you to specify bedrooms on the application and counts an unfinished basement as a bedroom. Adding a one-bedroom ADU can mean your existing system is no longer big enough, and that can be a big piece of the budget.
Call your county sanitarian early. It's the cheapest phone call in the whole project.
Foundation and slope
A flat lot with good soil and a simple crawl space is the simplest case. A sloped lot can turn into a walkout or a taller stem wall, which adds concrete and engineering. It can also be an opportunity, since a walkout adds usable space under the unit.
Access for the truck and crane
Modules arrive on a truck and get lifted by crane. If the truck can't get close, or the crane has to reach a long way over the main house, costs go up. This is one reason the factory does a feasibility study before you commit (see below).
Distance to utilities
Every foot of trench from the main house's power panel, water line and sewer line to the ADU is money. Placing the ADU closer to existing connections is often the single easiest way to save.
How we get you to a real number
You shouldn't have to guess. Here's the order we go in:
- Free first look. You send us your address and what you're thinking about. We take a preliminary look at the lot, zoning and access.
- Pick your models. Browse our ADUs and narrow it down to a couple.
- Feasibility study. The factory does a paid feasibility study of your site, and the fee is credited toward your home if you go forward. Our guide page has the current terms.
- Contractor estimates. Partner contractors price the site side (foundation, utilities, septic, set) against the finalized design. Now you're looking at factory price plus real local bids, not a guess.
That's the point where the all-in number is real, and you can decide with your eyes open.
Quick rules of thumb
- Treat the factory price as the start of the budget, not the budget.
- Rural lot with septic? Talk to the county sanitarian before you fall in love with a floor plan.
- The closer the ADU sits to existing utilities, the less you'll spend in the ground.
- State law is on your side in many places: our guide covers the Montana ADU and factory-built housing laws that require many cities and counties to allow ADUs and treat factory-built homes like other housing. Your local planning office still has the final word on your lot.
Want a real number for your lot?
If you're weighing an ADU and want to know what the site side might look like on your property, send us your address for a free site review. We'll tell you what we see, what we'd check first, and whether it's worth going further. No pressure either way.
Thinking about a modular home or ADU?
Send us the property and we'll take a free first look at what it can hold.